Aurora Battery Project Clears Key Connection Milestone

January 16, 2026
SiBrick

We are pleased to announce that the Australian Energy Market Operator (AEMO) has accepted the proposed Generator Performance Standards for the 140 MW Aurora Battery Energy Storage System (BESS), in accordance with the National Electricity Rules.

ElectraNet, South Australia’s transmission network service provider, has also confirmed acceptance of the full Generator Performance Standards package. This acceptance is valid for 12 months, subject to execution of a Transmission Connection Agreement (TCA).

Both AEMO and ElectraNet have advised that connection of the Aurora BESS will not result in an adverse system strength impact on other existing or committed generating systems.

1414 Degrees manages the BESS project and the broader Aurora Renewable Energy Precinct on behalf of SiliconAurora Pty Ltd (SiAu), which holds the Crown Lease over the 15.8-hectare site. To date, SiAu has invested over $3.5 million in generator studies and regulatory approvals to advance the development of the Precinct.

Following this milestone, AEMO has advised that its final due diligence assessment will commence once final technical models and detailed design information are submitted. In parallel, we will progress remaining technical deliverables and work toward finalising the Transmission Connection Agreement, enabling advancement of power purchase agreement (PPA) discussions with customers.

As previously announced, separate negotiations are required with the current sole user of the existing transmission line to enable reclassification of the line as a Dedicated Connection Asset, allowing open access to the National Electricity Market. The Company remains confident that agreement will be reached.

This connection milestone represents the first component of a broader Continuous Energy Hub planned for the Aurora Precinct. As outlined in the our announcement dated 9 January 2026, the site has potential to support future data centre and other developments, subject to commercial arrangements. This potential is underpinned by increasing global investment in AI-driven digital infrastructure and demand for firm, reliable electricity supply.

1414 Degrees Executive Chairman, Dr Kevin Moriarty, said:

“This milestone represents a critical regulatory step forward and allows the Aurora Precinct to move toward commencement in 2026. In addition to revenue from the BESS, it supports broader development opportunities, including data centre potential previously outlined by the Company.”

Read the full ASX Release here.