News from 1414 Degrees
New Appointments
We are pleased to advise that 1414 Degrees has appointed Dr Jordan Parham as Chief Operating Officer to lead the next phase in the Company’s development. Dr Parham will commence with the Company on 14 January 2019 from his current role as CEO of FCT Combustion’s...
Heat energy offers opportunity to transform global heat networks
The global renewables sector has largely directed its efforts toward development of new technologies to support the generation and storage of electricity. However, it is the use of heat energy, not electrical energy that dominates global energy requirements....
Quarterly Update: October 2018
Quarterly Update 1414 Degrees Limited (ASX:14D) is pleased to provide its third quarter 2018 update. HIGHLIGHTS $16.3 million IPO and ASX listing 10MWh TESS-IND first stage commissioning results better than anticipated November construction start agreed...
SA Water GAS-TESS announced to move late November
1414 Degrees Limited and SA Water have signed the Project Development Agreement (‘PDA’), to commence construction for the Company’s GAS-TESS device at SA Water’s Glenelg Wastewater Treatment Plant. This is the first installation of a 1414 Degrees product at a...
Global interest increases
1414 Degrees Limited (ASX:14D) is pleased to announce that attending a recent conference in the United States has led to increased interest from global markets. Our origins are in Australia a decade ago and our technology has long term, global relevance as renewable...
1414 Degrees lists on the ASX
1414 Degrees Ltd (ASX:14D) is today listing on the Australian Securities Exchange (ASX) after raising $27 million and gaining more than 2,100 shareholders since it became a public company less than 21 months ago. The latest raising of $16.3 million was at 35 cents....
10MWh Progress Update: September 2018
The first stages of commissioning of the TESS-IND have progressed very well, including successful runs for several hours. Commissioning is a multi-stage process from verifying individual components to operability of the control systems to optimising power generation....
ASX Listing, September 12
1414 Degrees Listed on the ASX - A Milestone in Australian Renewable Energy Innovation 1414 Degrees (ASX:14D) officially commenced trading on the Australian Securities Exchange (ASX) at 11am (AEST) on September 12, 2018. This marked a major milestone in the company’s...
ASX listing update: only 4 to go
Following the successful raising of $16.3 million as part of its IPO, 1414 Degrees is now in the process of formally listing the Company on the Australian Securities Exchange. In anticipation of some seed shareholders not being available to sign Restriction Agreements...
Progress update: TESS powers turbine
The first stage of the commissioning of the TESS has been a resounding success. Our engineers successfully ran the turbine, generating electricity for the first time using hot air from the TESS, a significant milestone. We managed to achieve approximately 30% of the...
IN THE MEDIA
msn: 1414 Degrees Strengthens Leadership with New Operations Head
@AuManufacturing: 1414 Degrees hires new GM
In Daily: Foreign investment for 1414 Degrees
In Daily: Woodside-backed 1414 Degrees launches hydrogen production project
@AuManufacturing: Towards 3% R&D – Innovation for process heat by Dr Mahesh Venkataraman
In Daily: 1414 Degrees secures rights to new University of Adelaide hydrogen tech
@AuManufacturing: 1414 Degrees and Vast progress energy storage project
Renew Economy: Reborn solar thermal and battery project seeks deal to plug in to transmission line to BHP mines
Australian Manufacturing: SiBox testing completed, 1414 Degrees moves toward commercialisation
Renew Economy: Woodside boosts investment in molten silicon energy storage hopeful